Storing
At site, the panels are mostly stored a while before installation. While storing, the following precautions must be taken.
Packages must be placed on 20 cm length wooden wedges in 2 meter distance. The EPS dowels between the packages must be also used here and the wedges on top of each other must be aligned.Paketler 2 paket üst üste alanda istiflenmelidir.
The packages must be stacked at the area as 2 packages on top of each other.
hey should be stacked as inclined so that the rain water does not accumulate on the packages and enter inside.
If the stocks will not be protected in a closed place, they should be covered with a water proof overlay so as not to form a pool. But at the same time,
attention should be paid to leave an empty space between the overlay and the panels for air circulation.The stocks must be checked whether the moist or water
enters into the packages despite the protection. Attention should be paid to stock the panels in a secure place against theft and impact. The packages must not be stocked on the passage roads.
If there is protective films on the panels, they must beremoved immediately after the installation is finished. If the installation will not start immediately, they must be kept in the shade or in a closed area at the construction site. Otherwise protective foil can stick on the metal by heat and can damage the painted surface during the attempts of removing.
Before and after installation, contact of substances that may lead sandwich panels corrosion such as earth, lime, mortar, fertilizers, acids, salts and alkalist must be avoided. The processes that can create scratches on the material must be also avoided.